Construction progress of the project «Marina Arcade»

Photo report of construction progress of the residential complex Marina Arcade at UAE, Dubai, Dubai Marina, Marina Arcade Tower.

Construction dynamics

Price range
2,7 M21,1 M
Delivery date
Q1 2017

Completion

100%
Developer
Quick consultation
Fill out the form and we will contact you shortly.

Construction progress

project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
Completed
100%
Actual
100%
Planned
100%
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
Behind
-3%
94%
Actual
94%
Planned
97%
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
Behind
-4%
91%
Actual
91%
Planned
95%
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
Behind
-8%
86%
Actual
86%
Planned
94%
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
Behind
-11%
79%
Actual
79%
Planned
90%
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
Behind
-20%
66%
Actual
66%
Planned
86%
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
Behind
-25%
58%
Actual
58%
Planned
83%
Behind
-35%
44%
Actual
44%
Planned
79%
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
Behind
-53%
16%
Actual
16%
Planned
69%
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
Behind
-55%
10%
Actual
10%
Planned
65%
project inspections
project inspections
project inspections
project inspections
project inspections
Behind
-49%
8%
Actual
8%
Planned
57%
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
project inspections
Behind
-38%
8%
Actual
8%
Planned
46%
Frequently Asked Questions

Quick consultation
Fill out the form and we will contact you shortly.
By using the service, you agree to our Terms of Service and Privacy Policy.

We value your feedback!

Help us improve by sharing your thoughts and experiences.

Realmond Logo

Unlock Your Dream Home with Us!

office 702, Emaar Square 6, Burj Khalifa Community, Dubai, UAE

By using the service, you agree to our Terms of Service and Privacy Policy.

© 2025 Realmond Real Estate. All rights reserved.